Spot the difference in two Primavera update

A
Amjad Hanan 👤 Member for 11 years 4 months

Dear Gents, 

We used to send primavera update to our planning manager on weekly basis. Is there any provision in primavera to spot the difference in progress for the only activities from the previous week.   

Your help in this concern is unfathomable! 

A
Amjad Hanan 👤 Member for 11 years 4 months

Thank you Mr. Kannan and Mr. Eoin , It works! 

 

@Zoltan, Is claim digger an add-in option in primavera? When I select claim Digger, it retrieve a mesage "The selected application: C:\Program Files (x86)\Java\jre7\bin\javaw.exe cannot be found." have experineced any issue as such ?

 

E
Eoin Flannery 👤 Member for 10 years 10 months

+1 for using baselines.

We would use an original baseline to display the Rev0 then use a second bassline as a copy of the previous weeks issue.

A trick we use is to save each weekly issue as a baseline (witht the issue date) but dont have it displayed.

So in essence we have 3 "live" basleine with each issue.

1: Original Rev 0

2: Last weeks basline

3: Copy of issue (not displayed)

 

Each week we issue the shcedule we would simply change the copy of last weeks baseline.

K
Kannan CP 👤 Member for 17 years 11 months

Amjad,

Set the last week project as the baseline for this week update. Create the filter to show the baseline dates for the previous week. compare it against the present update.

I hope this will help

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts