Resource question

Hello my friends 



I have question about resoruce assign .



After I putted all resource and assigned it on activities , Can I Know where is the activitiy i added the resource on it ? 

if i have resource (XXXX ) as example and i butted it on activitiy but i forget it ( forget which is this activity ) can i know that where is the activity i uploaded the recource (xxxx) on it ?

 

i hope my explain was good .

A
Ahmed Aziz 👤 Member for 11 years 9 months

Dear Ghidan,

go to the resource assignment window (its icon is under the WBS icon). then you can set a filter by resource to show each resource and its assocciated activities.