I have a nice resource histograme that shows my resource forecast stacked by a resource code that separates direct hires, contract workforce & agency staff. I can show the actual hours expended on a non stacked histograme. Does anyone know if it's possible to show them on a stacked histograme?
Yours hopefully
Tim
Stacked histogramme, can I show "actuals" on it?
Forum Sponsor
Top Posters
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
you are asking two different quesitons here
can you to show actuals on a non stacked ?
the answer is yes
can you show stacked actual on a histogram ?
it is easier to do in version 8.2 than 6.2 but it can be done.if you have the resouce codes set up then its easy
to show them stacked
view show on botom resource profile
in the lower left hand window click on the upside down triangle where it says Display and select Group and Sort By
next select customize
in the group by put in your resource code in there you can also change the font and color for each code
in the right hand window right click and select resource Usage Profile Options and select actual you can do this for either the units or the costs
as another method what you can do is to assign a role to each of your resources
then view show on botom resource profile in the lower left hand window click on the upside down triangle where it says Display and choose Select View then By role
then on the rigth hand side rigth click and select stacked histogram
now right click and select role usage profile options
this is where you give the roles the diffierent color and patterns that you want to use