Fellow Plannners,
Can some one here help me with removing the Decimal in BL Project Units Percent Complete? See the pic below

Fellow Plannners,
Can some one here help me with removing the Decimal in BL Project Units Percent Complete? See the pic below

Yes Zoltan,
Made all times units to 0 Decimal.
thanks
did you make the hour units zero decimals ?
Hi Ala,
Tried that, it does not work. There should be something else to remove the decimal diigits.
thanks,
pranab
go to edit
user prefernce and make decimal to 0