Error Msg

A
Ali Alali 👤 Member for 11 years 6 months

Hi Everyone,

I faced an error msg when deleting a project or make a copy of another project as following , I need a solutions please.

******************************************************                EXCEPTION  REPORT                  *  *****************************************************Date:          02-Dec-14          Executable:    PM.exe   Application:   Primavera P6 Professional R8.2 Event Code:    PRMDB-1567-D   Message:             PRM DBAccess Error: ORA-12952: The request exceeds   the maximum allowed database size of 4 GB             Context:        1: TCFormManager.SetToolbar    2: TDevxMainForm.BeforeFormShow    3: TfrmLogin.FormCreate     4:        5:        6:        7:        8:        9:        10:            Detail:        Type:        EprmDBSQLExecutionFailure    Object Type: TCVirtualQueryGrid        Database Error:       Error Code:     0                                                                                                                                           

Z
Zoltan Palffy 👤 Member for 16 years 10 months

you have reached the 4 gig a byte memeory limit for microsoft slq express.

the way to fix this is to open an old project and start to delete a few activiites

then start to delete a few more activiites 

this is a long and tedious process bcasue it takes memeory to delete data.

at some point you wil be able to delete severla activities at the same time

now you can delete the old projects

I would recommend creating another database to start any new projects 

 

 

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts