Hi,I am working on resource loading in my programme (P6 r7), I have completed almost 25% of the activities untill yesterday, but today when i started plugging in the budgeted units (matetrial), I am not getting the "Remaining Units / Time". I have also tried by plug in the units in the Remaing Units / Time and still I am not getting the Budgeted Units.- I also tried Checked and Check off "Drive Activity Dates by Default" in the general tab of Projects and the resource assignment.I am not convinient in import / export to/from Excel. Please advise meCheers
Remaining Units / Time
Forum Sponsor
Top Posters
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
this must be a number 8 ? 10 ? 12 ?
Hi,
My default unit is Budgeted Units
what is your default units/time ?