When exporting activity relationships to Excel, only get 10 characters in the predecessor & successor activity names, but when I export activities, get the entire name. How do I expand the number of characters in the relationships export?
Thanks
When exporting activity relationships to Excel, only get 10 characters in the predecessor & successor activity names, but when I export activities, get the entire name. How do I expand the number of characters in the relationships export?
Thanks
one thing to do it to create a Vlookup in the TASKPRED tab that references the TASK tab in excel.