How cost calculation can be changed from the starting date of the activity to finishing date

Hi Guys,

I prepared a cash flow report by customizing the planned & cummulative planned calue. The project activities start in March 2014 and the last activities fall in Feb 2016. Whereas the cash flow shows values only till Jan 2016. The corresponding value for Feb 2016 is zero since there are no activities starting in Feb 2016. I need the cost to be calculated based on the finishing date of the activity. 

Can somebody suggest how to fix it.

 

 

Z
Zoltan Palffy 👤 Member for 16 years 10 months

check your calendars and your resource calendars take a look at smaller increments for your time scale maybe in weeks or days in the view.

Also check your resource to see if drive activities dates by default is checked.

Under the resource check you default units/time it should not be 1 or 0

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts