Duration changing with resource changes

T
Tom Tom 👤 Member for 11 years 9 months

Hello All,

     I am having trouble with my project duration changing everytime I change the max units/time of a rersource. What am  I doing wrong. I dont not want a resource to recalculate any of my durations.

Thanks

Z
Zoltan Palffy 👤 Member for 16 years 10 months

go to your project directory

make sure that your project is highlighted and open

look at the defaults setting look at the duration type change it to fixed duration & units. Now when you add new activites the resource will not drive the duraitons.

now you have to fix the duraiton type for the existing activities

go to activities add column

look under General and add Duration Type

change the top one to fixed duration & units then do a fill down for the remainder of the activities

this should fix it.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts