Hi All
Just wondering if theres a way of removing all activity relationships to external projects via a global change?
Thanks for any pointers
V
Hi All
Just wondering if theres a way of removing all activity relationships to external projects via a global change?
Thanks for any pointers
V
why not go to the scheduling option and turn OFF the link to external projects
Hi kutty,
I am afraid you cant remove the relations by a global change instead tgere are two other ways:
1. Copy and paste the project and unmark "copy aexternal activity relations"
2. Export to excel (only relationships) open the excel sheet "taskpred". Filter the activities from other project, put a " d" in tge column named "delete this row", import to primavera.
Aziz