Open Ended Milestones

Hello,

Can Monitoring Milestones like "Receive all Equipment", "Finish all MEP works" be kept open-ended if it does not have any single logical successor?

if otherwise, lot of float is generated (calculated upto project end).

How do you deal with this?

 

-Haroon