Remaining cost & Project Cost are after updating

 

Hi,

I am new to P6, i am finding difficulty cost, in my program if i am updating the % complete of the activity my earned value is getting updated but my total budget cost and remaining cost are same. remaining cost is not getting updated.

R
Ravi Katare 👤 Member for 11 years 10 months

Hi,

Are you updating the remaining resource units? If not do it

- Ravi