Hi,
Can anyone please explain me how the "Reamaining Early cost" and "Remaining Late cost" are being calculated?
Generally, What is the logic behind this calculation?
Regards,
V.K.Balaji
Hi,
Can anyone please explain me how the "Reamaining Early cost" and "Remaining Late cost" are being calculated?
Generally, What is the logic behind this calculation?
Regards,
V.K.Balaji
Hi VK
The principle is very simple:
The first ninety percent of the work takes the first 90% of the cost.
The last 10% of the work takes the last 90% of the cost.
Best regards
Mike Testro