When some layouts are already saved in P6. After importing some baseline as well as updated and on assigning that layout gant chart is showing emptry. so what is the successful solution to apply that layout
Layout
Forum Sponsor
Top Posters
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
If gant chant is showing empty, is it because a filter has been saved as part of the layout, that is returning zero activities.
So either the filter in layout is wrong, or the project does not have the right codes for the filters to work.
Either way: check your filter