Hi guys,
I am using Primavera P6v7 but I found some problem about the "auto compute actuals".
I don't know why the checkbox "auto compute actuals" is flagged on activities and for each resources but it does not work.
For info my resources are unpriced price/units = 0 , by avoiding to display costs to client.
Is there anything wrong? What am I forgetting? Some project default/setting missining?
Thanks in advance
Michele
Hi,
Could you please be specific? I am not getting question, what your doubt is.
Auto compute Actual is mainly used for updating schedule by getting actuals from Progress Reporter/Team Member modules and only those activities and resources will get updated for which Auto compute Actual checkbox is selected.
- Ravi