How to restore the Primavera data

Hi Experts ,

 

Due to some reasons my Primavera was corrupted, I try too much to save but I am fail to do, But I copy the data folder from C drive in Oracle folder, So please help me how to restore that data which I copy from my Auto backup folder.

 

Thanks

I am in a very very trouble pls. help me.

M
Muhammad Sohail Ashraf 👤 Member for 12 years 5 months

Can u please give me your Email ID, So i can explain you in brief.

 

I am using Primavera P6 R8.2.

Please give me your email ID .I am very thankfull to you.

 

J
Jehad Aldaoud PMP, PMI-SP 👤 Member for 15 years 8 months

please see the folowing procedures 

 

ckup stage 
 
first we make 
 
1- At the SQL Command Line prompt, enter the following command:
 
CONNECT SYS/password AS SYSDBA
 
2- At the SQL Command Line prompt, enter the following command:
 
SHUTDOWN IMMEDIATE
 
3-At the SQL Command Line prompt, enter the following command:
 
STARTUP MOUNT
 
4-Enter the following command:
 
ALTER DATABASE ARCHIVELOG;
 
5-Enter the following command:
 
ALTER DATABASE OPEN;
 
6- go to START>All Programs>Oracle Database>Backup Database
 
7- copy the file c:\oraclexe to D driver
 
Restore Stage 
 
1- copy file FLASH_RECOVERY_AREA from file in the D Driver oraclexe to 
 
C:\ORACLEXE\APP\ORACLE\FLASH_RECOVERY_AREA\
 
2- after go to START>All Programs>Oracle Database>Restore Database
 
when it's request the location of FLASH_RECOVERY_AREA
 
copy this location and paste it in the dos 
 
C:\ORACLEXE\APP\ORACLE\FLASH_RECOVERY_AREA\

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts