Hi
I request you to guide me on the below issue
I have three contractors, one is Engineer and another is Procurement, and Construction, all give their schedule, how I could link all together, first to form a baseline and then periodically, if they send the update, how to replace the old file to new one.
please guide
Thanks
Venkat
Venkat,
You can use P6 enterprise server to establish an overall IMS (Integrated Master Schedule) which allows you to set-up a Master and sub nodes beneath for individual EPC contractor plans while also recognising task interdependencies & logical relationships
Cheers,