Baseline budgeted units update

Dear all,

I have to create a second baseline (BL2) with updated BL1 Labor units but I want to keep same dates & durations as in BL1.

In short : BL2 Labor units = Budgeted Labor units of the current project and BL2 dates & Durations = same as BL1

Does anyone know how to do this without updating each BL1 Units manually ?

Thanks