why my Baseline & Actual units showing different after assigning the current project as a baseline ?

I
Irfan Khan 👤 Member for 16 years 11 months

dear all,

i encountered with the problem which seems something unrealistic : means u update my schedule & than i made a copy the current schedule as a my baseline.

here when i am looking @ my units its showing different for past month. whereas it should be the same asplanned.

please check the attachment for reference.

thanks…... [[wysiwyg_imageupload::]]

p6_prob.png

R
Ravi Katare 👤 Member for 11 years 11 months

Hi,

Run GC to replace Planned start & finsh with start & finsh.

- Ravi

C
Charlie Daniels 👤 Member for 12 years 6 months

HI Irfan,

 

Not sure that this will help, I had a similar problem recently.

If I looked on the Gantt Chart the Baseline Bar didn't line up with the current bar.

The dates were not lining up either. (I also created a new baseline using the current project)

I checked the following:

1. The correct Baseline was assigned

2. The correct Columns were being displayed (relevant to that baseline)

3. The correct baseline bars were selected on the Gantt Chart

After all these were confirmed and correct it still dodn't match.

I aligned the original duration with the remaining duration using global change, this seemed to have sorted the problem out.

 

I hope this can help with your issue?

 

Regards

Charlie

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts