BCWP Issue

Hi all,

Apologies in advance if I've posted in the wrong thread and also if my explanation of my issue isn't that clear, I am fairly new to planning/P6!

I'm using Primavera P6Image removed. v8.2 and have noticed that historic BCWP seems to be moving from previous months, to the current month, even when no progress has been recognised that month.

 

I have the original baseline plan set as the primary baseline for the forecasted plan. The forescasted plan is the one I make my progress updates on. I am having an issue with activities which are in progress. Say for example I have an activity which is 50% complete, with a cumulative BCWP of £45k (£15k in July,£15k in August and £15k in September). Say in this example there was no progress in October, so the cumulative BCWP is still £45k at the end of October, when I move the data date to the beginning of the next reporting period (beginning of November), P6 is taking a slice of all previous months BCWP, so in this example from July, August and September and putting it in October, distorting the historical BCWP (cumulative remains the same at £45k). 

 

Now, I'm assuming there is a setting somewhere, that I have accidently changed that is making this happen, but I can't figure out what it is and how to stop it!

 

Any suggestions would be greatly appreciated.

Thanks,

Ash

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts