Renaming/Changing Resource ID

Hi All,

I am trying to find a faster way to change/rename exsisting resource id's (about 500). I have tried import/export but that does not seem to change the resource id. And it seems that this cannot be done by global change either.

Any assitance would be appreciated.

Regards

 

H.

S
Sunil Babu 👤 Member for 15 years 7 months

Hi Harpreet,

Export to excel sheet, edit and import.

Regards,

Sunil