Hi,
1. When I use the data line to update my activities, it automatically completes certain tasks which should still be in progress?
2. Once some activities have been progressed, I F9 and some of the increase in duration?
3. If I manually select a task 'Start' or Finish then the successor will fall back to the data line?
I have a really large schedule and these occurrunces are making it hard for me to manage the schedule.
Please any help?
Thanks