Progressin activities with Data Line Issues

Hi,

 

1. When I use the data line to update my activities, it automatically completes certain tasks which should still be in progress?

2. Once some activities have been progressed, I F9 and some of the increase in duration?

3. If I manually select a task 'Start' or Finish then the successor will fall back to the data line?

 

I have a really large schedule and these occurrunces are making it hard for me to manage the schedule.

 

Please any help?

 

Thanks

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts