Assigning last month updates as baseline for this months updates

Dear All,

Whenever i assign last project updates for current month baseline all the actuals till last months updates gives wrong dates. It creats lots of confusion whenever i wanted to compare the current status with the last months status.

Please help me if anybody have the solution for this problem.

Thanks & Regards,

Girish Bhave

 

K
Kaif Mohsin 👤 Member for 15 years 3 months

Dear Girish,

Go to the Admin, Admin Preferences, Earned Value Calculation Settings and change it to "Budgeted values with current dates"

This will show you the actuals from the last month updates when it is assigned as a baseline to the current month update.

Best Regards,

Kaif Mohsin

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts