Dear All,
Whenever i assign last project updates for current month baseline all the actuals till last months updates gives wrong dates. It creats lots of confusion whenever i wanted to compare the current status with the last months status.
Please help me if anybody have the solution for this problem.
Thanks & Regards,
Girish Bhave
Dear Mohsin,
Thanks for sharing , It realy works.
Regards,
Girish Bhave
Dear Girish,
Go to the Admin, Admin Preferences, Earned Value Calculation Settings and change it to "Budgeted values with current dates"
This will show you the actuals from the last month updates when it is assigned as a baseline to the current month update.
Best Regards,
Kaif Mohsin