Placing Gaps in the Timescale

D
Dan Hood 👤 Member for 12 years 8 months

I frequently have projects that have long gaps in the middle between two very hectic segments.  As always, managers want to see the entire schedule on a single paper width.  So the example below:

 

Six months straight work, followed by nine months of nothing, followed by one year of work.  Is there any way for me to set the timescale to somehow show a nine month gap as just one or two cell column widths while the rest is set to YEAR/MONTH when we are actually doing work?  Looking for something similar to a drafting break on an engineering drawing but in the timescale.

 

Sorry if this is a repeat of another forum question.  If so, just link me to it for reference.  Thanks.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts