Drive Activity Dates

M
mani M.R 👤 Member for 16 years 10 months

Hai

Some of the activity Resource Original Duration is not Equal Activity original duration . This issue occur where single activity have Multiple resource .  Activity Type is task Dependent , Duration type is Fixed Duration & Units /Time, Percentage Complete is duration Whether Default Drive Activity Dates option is to be Clhecked even the Activity Type is task dependent (Drive Activity Date option will be checked where Activity Type is Resource Dependent)  RegardsMani    

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts