Colour Coding Bars

D
David Leek 👤 Member for 14 years 9 months

Hi,

Hopefully someone out there can help me out.

Within a P6 programme I have colour coded procurement bars so they can be rolled up but the different phases can still be veiwed.  To do this I have created new bars and apply filters to them (one for each of the stages).  This works fine and im happy with the results.

The problem comes when I have to copy the programme. I then loose the ability to show the bars in different colours. They still have the filter applied to them but show up as whatever colour bar is the lowest within the bar window.

How do I solve this or is it something that just cant be done?

Thanks in advance.