Hi to all experts,
After migrated form Primavera v 6.2 to 8.2 i have problem wbs summary duration. I import file to latest version but when I choose global calendar default (ex 7 days or 6 days/week calander) wbs summary duration not changing in R8.2 but in V6.2 it works.
Kindly provide me asisstance to anyone know solution of this problem?
Thanks in advance.......
Hi Melvin, Latest P6 based the summary (if calendar is not the same for all activities under that WBS) from Project Calendar not from Default calendar. Here's from P6 Help, "if all the activities are not using the same calendar, then the values are calculated as follows: