Primavera v 6.2 to 8.2 - WBS Summary Duration using Global Calender

Hi to all experts,

 

After migrated form Primavera v 6.2 to 8.2 i have problem wbs summary duration. I import file to latest version but when I choose global calendar default (ex 7 days or 6 days/week calander) wbs summary duration not changing in R8.2 but in V6.2 it works.

Kindly provide me asisstance to anyone know solution of this problem?

 

Thanks in advance.......

F
Ferdinand U. 👤 Member for 18 years 10 months

Hi Melvin, Latest P6 based the summary (if calendar is not the same for all activities under that WBS) from Project Calendar not from Default calendar. Here's from P6 Help, "if all the activities are not using the same calendar, then the values are calculated as follows:

  • If all the activities under the group band are in the same project, then rolled up duration and unit values are calculated using the project’s default calendar.
  • If all activities under the group band do not belong to the same project, then rolled up duration and unit values are calculated using the default global calendar."

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts