Problem - Resources being phased after activity completion

Hi

This relates to P6 release 6.0

We are noticing a problem where the resource histogram profiles are running well past the activity completion dates.

Does anyone have some idea as to why this is happening?

We think it may be a software error where a previous resource phasing distribution has not been removed/replaced.

A
Andrew Podolny 👤 Member for 21 years 6 months

Please also ensure that the drive activity dates is checked on and the lags are 0 for your resource assignment:

K
Khaja Sharief 👤 Member for 17 years 8 months

One more reason could be that, there are activities with negative float which is because of unsatifactory constraints attached to activities in the network. Remove the constraints to the activities connected with the activity's network path.

R
Raymund de Laza 👤 Member for 16 years 6 months

Stephen,

I suggest to investigate the Calendar assigned with the Resources. View the Start and Finish date of the Primary Resource.

 

Hope this will help.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts