Hi All,
I'm cleaning up a database and I was unsure if there was an easy way to change global calendars to project calendars?
All help/ thoughts appreciated.
Regards, Kylee.
Hi All,
I'm cleaning up a database and I was unsure if there was an easy way to change global calendars to project calendars?
All help/ thoughts appreciated.
Regards, Kylee.
Hi Kylee,
The only way you can change your calendar from global to project is by using the SDK (Dictionary6.xls), otherwise, Mr. Paul suggestion is to copy the global to project calendar is the best way.
Thanks
Arnold
Kylee
You may not change them only copy them.
Regards
Paul E HarrisBSc Hons,
Certified Cost Engineer, PRINCE2 Practitione
Managing Director and President
Eastwood Harris Pty Ltd, Australia
www.eh.com.au, www.eastwoodharris.com, www.primaskills.com.au and www.primavera.com.au
Project Control Consultants and Planning and scheduling software book and training material publishers