delays/advance (days) ?

What is the easiest way to know delays/advance (days) ? p6

Thanks

G
Gary Whitehead 👤 Member for 17 years 2 months

1) Create a baseline to measure delays / advance from (Project Menu > Maintain baselines)

2) Assign that baseline to your current project (Project Menu > Assign Baselines)

3) Show the colums "Variance -BL Project Duration", "Variance -BL Project Finish Date", and "Variance -BL Project Start Date" (View Menu > Columns > "Durations" group)

4) For a visual represrentation, show the baseline bar in the gantt chart (View Menu > Bars)