Resource Planned Value

S
sneh kumar 👤 Member for 13 years 11 months

Dear All,

In my schedule each activity has more than 5-6 resource assigned to it. For updating the actual, our discipline engineers want to know the planned value of each resource on the Datadate (for reference). I could able to get the overall palnned value but not able to get the planned value of each resource.

Is it possible to get the planned value of each resource on the datadate by running the schedule?

Please suggest. 

A
Andrew Podolny 👤 Member for 21 years 6 months

Hi Sneh.

If your resource assignments share same calendar and connected to activity dates - you can refer to overall activity planned % on date. However if you are using resource assignments lags or different calendars the only way to get proper planned % for each assignment is to open your baseline and in resource assignments view calculate what % should be completed on data date. Primavera doesn't provide with planned % and all  EV - related data at resource assignments level.

Regards,

Andrew

A
Alain De leon 👤 Member for 13 years 11 months

Hi sir/ma'am

go to resource usage spreadsheet, Highlight your sepecific resource, and customize your spreadsheeet field. hope it helps

Godbless

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts