Hi all,
I've been asked to give a presentation of the SPI & CPI trend of a project based on the last 12 months update. Is there a way that I can assign each update's baseline and get the CPI & SPI? Not sure how to do that if we haven't captured each month in the reports.
If you used the 'Store period performance'facility after each progress update, then you have all the raw data (planned/earned/actual) to make the spreadsheet. If not, it is quite a job. You will need to restore each baseline, and extract each period's data into a spreadsheet.