Activity Type = WBS Summary

Hi All,

 

I just need some clarification,...............Do WBS Summary Activities drive other Activities if used as Predecessor?

 

I think not but would appreciate confirmation.

Cheers,

 

Rod

D
david kelly 👤 Member for 10 years 4 months

no!

WBS summary activities and LoE activities can have no schedule impact, and cannot be levelled

R
Rodel Marasigan 👤 Member for 19 years 8 months

Hi Rod,

The WBS summary activity functions more like a "hammock" activity, summarizing the activities within the WBS element it represents. While it can be linked to other activities for dependencies, it doesn't directly influence the scheduling or sequencing of those activities, unlike MS Project, where the summary bar can drive activity when linked to a network or used as a predecessor.

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts