Hi All,
I just need some clarification,...............Do WBS Summary Activities drive other Activities if used as Predecessor?
I think not but would appreciate confirmation.
Cheers,
Rod
Hi All,
I just need some clarification,...............Do WBS Summary Activities drive other Activities if used as Predecessor?
I think not but would appreciate confirmation.
Cheers,
Rod
no!
WBS summary activities and LoE activities can have no schedule impact, and cannot be levelled
Hi Rod,
The WBS summary activity functions more like a "hammock" activity, summarizing the activities within the WBS element it represents. While it can be linked to other activities for dependencies, it doesn't directly influence the scheduling or sequencing of those activities, unlike MS Project, where the summary bar can drive activity when linked to a network or used as a predecessor.