Earned Value at activity level
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
J,
Were using OPP with Cobra and all EV reports came from Cobra so never noticed....no longer using either.
John/Frank
My response was "In OPP v3.1 there is an option to allocate an EVT to each activity HOWEVER OPP does not actually use that information. For example, if you added an EVT of 0-100 it would let you enter in 50%."
I was referring to how open plan works not how Earned Value works. In OPPv3.1 you can assigned an EVT to each activity HOWEVER it doesnt use that information THEREFORE a user CAN enter in 50% on an activity which was meant to be 0-100 and it WILL calculate the EV at 50% of BAC.
J
Frank is correct. Also, if you are using progress calculations to compute Physical Percent complete you must check the option to Base Physical Percent Complete on EVT.
J,
0-100 means you do not earn any value until you reach the 100% mark....you can still be 50% complete and you will find the earned value reported is $0 and will remain so until you reach 100% complete.
HTH
In OPP v3.1 there is an option to allocate an EVT to each activity HOWEVER OPP does not actually use that information. For example, if you added an EVT of 0-100 it would let you enter in 50%.
J