Remaining Work Hours profile in Gantt Chart?

Hi All,

 

Is it possible to get this P6 view in MSP? I am displaying the Activitiy list on the Table side and on the Gantt charty side I have the timeline and also the Activity Work Profile Remaining Work Units.

 