MS Project 2016 - Is there a way of changing the relationship of a group of selected activities from FS to SS

Hi, 

Is there a way of changing the logic of a group of task's from  FS to SS?

 

regards 

 

Pranab

B
Bogdan Leonte 👤 Member for 13 years 11 months

Show predecessor and succesor columns, copy paste in excel, delete the values from ms project, find and replace in excel FS with SS copy paste back in MS Project.