Hi, 

Is there a way of changing the logic of a group of task's from  FS to SS?

 

regards 

 

Pranab

B
Bogdan Leonte 👤 Member for 13 years 9 months

Show predecessor and succesor columns, copy paste in excel, delete the values from ms project, find and replace in excel FS with SS copy paste back in MS Project.