MS Project 2016 - Renumber wbs of selected task is greyed out in MS project

Hi All, 

 

I am using MS Project 2016 and want to renumber a selection of activities but the renumber wbs selected task in ms project 2016 is greyed out.  I have tried the task sheet view and removing the autofilter, nothing works

 

Please help. 

 

regards

 

Pranab 

A
Alexandre Faulx-Briole 👤 Member for 23 years 6 months

Hi Pranab,

you need to select several tasks together; when you select only one task, you can only renumber the whole project

Alexandre