While changing the timescale from Days to monthly or quarterly or yearly in MS project, I'm getting the error of "Invalid argument" because of that, I cant able to change the timescale in MS project and the same MPP file I can able to change timescale in my colleagues laptop and its not able to change timescale in my laptop.

Kindly suggest.

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Nathan,

make sure the lower level in the timescale is not larger than the upper one:

for instance upper level = week, step: 1 is not compatible with lower level = days, step: 8

if the problem is not this one, I suggest you re-install MS Project

Alexandre

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts