Dear all readers,
In Microsoft Project 2007, there was a function which enable us to know which predecessor out of other predecessors is driving the critch path, this function is no longer exists in later version.
Could anyone teach me, if I want to squeeze the critical path, and I trace back from the completion date backwards. However . some task have many predecessors and could I know which one is driving rather than I have to squeeze all predecessors.
Thank!
Regards,
Gary
The "driving" predecessor of a critical path activity will be the one that's critical, i.e., the one that has critical path drag (unless you've used a scheduling constraint).
Additionally the drag of the critical path activities will show you where you might go to "squeeze" the critical path and by how much. Tom Boyle's BPC Logic Filter is an add-on to MSP that computes critical path drag.
Fraternally in project management,
Steve the Bajan