HI,
I have prepared schedule for building and assigned cost also but while after updating more than 50% of work as completed, parent WBS is at 11% only.
Task NameBaseline DurationBaseline StartBaseline FinishCostPredecessors% CompleteSchedule for Anchorage Building1463 daysWed 06-12-17 08:00Thu 29-09-22 17:00₹ 2,455,692,677 11% Structural work1165 daysWed 06-12-17 08:00Wed 06-10-21 17:00₹ 1,180,088,110 100% Sub Structure- Tower337 daysWed 06-12-17 08:00Wed 16-01-19 17:00₹ 265,569,460 100% Sub Structure- Podium486 daysThu 29-03-18 08:00Tue 05-11-19 17:00₹ 78,952,180 100% Super Structure857 daysWed 12-12-18 08:00Wed 06-10-21 17:00₹ 835,566,470 100% Non Structural work932 daysWed 04-09-19 08:00Thu 29-09-22 17:00₹ 1,031,195,775 0% Masonary & Finishing works927 daysWed 04-09-19 08:00Fri 23-09-22 17:00₹ 955,715,719 0% Handing Over171 daysFri 11-03-22 08:00Thu 29-09-22 17:00₹ 75,480,056 0% Other1460 daysWed 06-12-17 08:00Mon 26-09-22 17:00₹ 244,408,792 0% Professional fee1165 daysWed 06-12-17 08:00Wed 06-10-21 17:00₹ 27,879,2404SS0% Escalation1130 daysMon 09-07-18 08:00Thu 31-03-22 17:00₹ 148,073,7404SS+180 days0% Contingencies1460 daysWed 06-12-17 08:00Mon 26-09-22 17:00₹ 68,455,8124SS0%
Johan,
You asked, "What are the key influences for the forecast finish to reflect an October 2019 date whilst I know for a fact that the activity will be completed before end of June?"
Possible influences on the forecast delay of remaining work for task 2447 are:
1. This task has started out of sequence (i.e. its predecessor was not complete) AND "Split in-progress tasks" Schedule option is checked, AND the incomplete predecessor is delayed until October. As for all out-of-sequence progress, fix the relationship that you know to be wrong.
2. MFO or FNET constraint in October is applied to the task, OR ALAP constraint is applied to the task.
3. The Resume date of the task has been delayed by one of the following:
- manual entry or other incorrect update procedure;
- resource leveling.
4. Resource assignments have been delayed or otherwise modified by user entry or by the resource leveler.
Good luck, tom
Hi,
I have a query with regards to an issue I have experienced in Microsoft Projects.
Below extract contains an activity: “ Install P02-581-CNV-001 Crusher Discharge Chutes”, Activity ID 2447. This activity has an Actual Start of 1 April 2019 and progressed to 30%. What are the key influences for the forecast finish to reflect an October 2019 date whilst I know for a fact that the activity will be completed before end of June? The schedule is resourced and therefore progress recorded in % Work Complete.
ID
Task Name
Remaining Duration
% Work Complete
Actual Start
Actual Finish
Start
Finish
2434
P02-581-CNV-001 Installation SMPP
79.1 days
61%
15 Oct '18
NA
15 Oct '18
10 Jan '20
2435
P02-581-CNV-001 Steelwork Erection (89.65t)
21.63 days
85%
15 Oct '18
NA
15 Oct '18
26 Aug '19
2436
Erect P02-581-CNV-001 Grid 1 to 5 Structural Steel
2.1 days
85%
15 Oct '18
NA
15 Oct '18
05 Jun '19
2437
Erect P02-581-CNV-001 Grid 6 to 9 Structural Steel
2.1 days
85%
26 Oct '18
NA
26 Oct '18
20 Jun '19
2438
Erect P02-581-CNV-001 Grid 10 to 14 Structural Steel
2.1 days
85%
29 Oct '18
NA
29 Oct '18
29 Jul '19
2439
Erect P02-581-CNV-001 Grid 15 to 18 Structural Steel
2.1 days
85%
14 Nov '18
NA
14 Nov '18
26 Aug '19
2440
P02-581-CNV-001 Handrailing and Grating (232m x 273m²)
16.82 days
85%
15 Jan '19
NA
15 Jan '19
03 Sep '19
2441
Erect P02-581-CNV-001 Grid 1 to 10 Handrailing & Grating
1.5 days
85%
15 Jan '19
NA
15 Jan '19
10 Jul '19
2442
Erect P02-581-CNV-001 Grid 10 to 18 Handrailing & Grating
1.5 days
85%
30 Jan '19
NA
30 Jan '19
29 Jul '19
2443
Erect P02-581-CNV-001 Grid 17 to 21 Handrailing & Grating
1.5 days
85%
30 Jan '19
NA
30 Jan '19
14 Aug '19
2444
Erect P02-581-CNV-001 Grid 21 to 26 Handrailing & Grating
1.5 days
85%
28 Jan '19
NA
28 Jan '19
03 Sep '19
2445
P02-581-CNV-001 Platework Installation (2.6t)
39.9 days
63%
01 Apr '19
NA
01 Apr '19
29 Oct '19
2446
Install P02-581-CNV-001 Head Chute
0 days
100%
13 May '19
20 May '19
13 May '19
20 May '19
2447
Install P02-581-CNV-001 Crusher Discharge Chutes
1.47 days
30%
01 Apr '19
NA
01 Apr '19
23 Oct '19
2448
P02-581-CNV-001 Mechanical Installation
96.22 days
18%
22 Apr '19
NA
22 Apr '19
28 Nov '19
2449
Install P02-581-CNV-001 Drive, Gearbox and Pulleys
4 days
0%
NA
NA
29 Oct '19
05 Nov '19
2450
Install P02-581-CNV-001 Idlers, Free Issue Material
2.4 days
20%
22 Apr '19
NA
22 Apr '19
18 Nov '19
2451
Configure P02-581-CNV-001 Take Up
0.2 days
90%
22 Apr '19
NA
22 Apr '19
21 Nov '19
2452
Install P02-581-CNV-001 Belt & Splice
4 days
0%
NA
NA
21 Nov '19
28 Nov '19
Thanks,
Johan
Rushikesh,
Good luck, tom