Duration In Days

Dear All;

 

I am trying to see "Finish Date" - " Actual Start Date" to calculate "how much days i need if my task is late. for example;

 

i planned to complete a task in 10 days, i am in 5 th day of my project and i realized that i need 2 days more to finish this task. so i want to calculate "finish date"- "actual start date"

 

Thanks a lot.

S
Susanna Kate 👤 Member for 6 years 11 months

Hi,

You said "i am in 5 th day of my project and i realized that i need 2 days more to finish this task".

Is it 2 more days in addition to the 5th day (when you realized that) or 2 more days in additon to the 10 days?