Ideally in forward scheduling you specify As Soon As Possible (ASAP) constraints to commence your tasks at the earliest possible dates. So is it therefore redundant to specify a Start No Later Than (SNLT) constraint on a particular task? Let’s examine this question http://ow.ly/BAl03012FLI
Microsoft Project and Start No Later Than Constraints Explained
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Emily,
Applause for another well-written introduction to the concept.
Three quibbles related to emphasis: