Revision of baseline

Residential project of P + 18 with conventional shuttering for RCC work.

When i need to revise the baseline considering the actual dates when my RCC work has completed 50% i.e. 50% RCC slabs casted.

WHen i am revisiong the baseline considering the actual casting dates of slabs, activities changed to non critical, but practically RCC work has to be critical in the schedule isnt it ?

What should be the overall approach while revisiong the baseline considering actual dates & my 70% project is balance approx.

Gaurav 

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts