While tracking the project schedule i am finding problem. Some activities taking more duration then it was planned, so while updating the schedule i have entered actual start, remaining duration. Then the % completion is taking automaticallty. But the project summery task % completion is showing very much higher then it actually completed. How to solve this. Is there any other process to do the correct tracking. It will be very much help to me if anybody can answer me.
% complete at summary tasks
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
The % Complete is % Duration and will sunmmerise at Summary Levle based on the proportion of the total Actual Durations over the total of durations.
The Physical % Does not summerise.
This leaves % Work, so you would have to assign resources or you could do something with Custom Fields and formulae.
Regards
Paul E Harris
BSc Hons, Certified Cost Engineer, PRINCE2 Practitioner
Managing Director and President
Eastwood Harris Pty Ltd, Australia
http://www.eh.com.au, http://www.primavera.com.auand http://eastwoodharris.com.
Project Control Consultants and Planning and scheduling software book and training material publishers
Primavera P6 Version 8.3 eLearning available from http://www.primaskills.com.au/project-management-training/