Hi all,
I´m sitting on a concern that I hope you can help me with.
I have diffrent work packages that need diffrent calenders. I creat the calenders of the various jobs that exist.
What happens is that if I plan more then 8 hours a day so shortened duration down and make my activity shorter. I want to add 10 days, but the pace of work at 12 hours a day.
How can I do this?
Greatful for a quick reply
Regards
Dan
Thank you!
The problem got slowed yesterday
/Dan
Dan,
you need to create a seporate calendar and assign it to this spesific task:
See the link below:
http://office.microsoft.com/en-gb/project-help/set-working-times-vacati…
Consider also Task option "Scheduling ignors resource calendar"
Regards.
Anyone?
/Dan