very simple, been using P6 for to long and cannot do a simple exercise to produce a overall total project resource profile when i have and number of different resources. This must be simple but i cannot see it in 2010??
thanks in advance
very simple, been using P6 for to long and cannot do a simple exercise to produce a overall total project resource profile when i have and number of different resources. This must be simple but i cannot see it in 2010??
thanks in advance
Daniel,
Not 100% sure what you are looking for, but did you try Resource Usage view?
See example below of the Gantt chart view as well as Resource Usage view for the same project
Regards.
Evgeny