Fixed duration, fixed units, fixed work, effort driven. How and why and when use all of it?

E
Evgeny Z. 👤 Member for 18 years 4 months

Dear all,

If I look at it, Microsoft Project effectively has 5 types of tasks (fixed duration, fixed units, fixed work. Plus each of them can be either effort driven or not effort driven, except fixed work, which is always efforts driven)

I  am using MS Project quite for a while, but I could never really understand, why Microsoft effectively has 5 types of tasks, why it is needed, and in which situation use one and not the other.  For my schedules I use most of the time fixed duration and sometimes fixed work.

Does anyone has a good guideline about this?

Regards.

Evgeny

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts