I am working a relatively simple schedule in MS Project but the clien wants me to show the work units in resiurce usage as days, not hours. Is that possible? And how?
Regards
I am working a relatively simple schedule in MS Project but the clien wants me to show the work units in resiurce usage as days, not hours. Is that possible? And how?
Regards
Many thanks!
Sandy,
not only possible, but so straight away!
File, Options, Schedule, "Work is entered in" ...
Alexandre