How to calculate % work done

A
Ashik GB 👤 Member for 15 years 7 months

Hi Friends,

I have a small querry regarding how to get the information on calculation of Planned % work done for the particular month from Main Schedule.

For Ex: if the project duration is 365 days from Jan1st to dec31 st with 100% Scope, in that how can i know what is the planned % work for the month of any particular month?

 Please can any one help me for this?

Regards,

Ashik

 

A
Alexandre Faulx-Briole 👤 Member for 23 years 6 months

Hi Ashik

display "Task Usage" view, the set the time scale to month, right-click the distribution panel (rightmost panel), and select the "Baseline Work" field

as MS Project does not have a "% planned work" field, you will have to compute the %tage by yourself

Alexandre

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts