I have a small querry regarding how to get the information on calculation of Planned % work done for the particular month from Main Schedule.
For Ex: if the project duration is 365 days from Jan1st to dec31 st with 100% Scope, in that how can i know what is the planned % work for the month of any particular month?
Please can any one help me for this?
Regards,
Ashik
Hi Ashik
display "Task Usage" view, the set the time scale to month, right-click the distribution panel (rightmost panel), and select the "Baseline Work" field
as MS Project does not have a "% planned work" field, you will have to compute the %tage by yourself
Alexandre