MSP 2012

Hi all,

i have a couple quick questions.

ill explain what im after then maybe you could point me in the right direction as to where i am going wrong.........

basically i have a programme set up with fixed costs, resource costs and timescales - everything you would expect. when i come to update my project with actuals i would like to keep the  actual activity durations and incurred costs as something completely different.

i want to simply have the activitys and the associated costs as programmed totally seperate to stop it messing up my actuals? does this make sense?

for example - i have site supervision as an activity with 100 man hours spread over three resources. when i update the projects status percent complete to say 50%. 50 man hours has been automatically calculated? - with disregard to what they have actually done - for which i want to input seperately, i want to be able to progress the activity but without the incured cost of hours associated.

i think i have missed a fundamental  here when i have set up each of the activities with regards to how i am wanting to record my costs........

hope im making sense

thanks

 

steve

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts